Adani starts work on Carmichael Mine

Published by , Editor
World Coal,


Adani has recently started work at the opencast mine to remove the layers of overburden above the coal seams.

Adani Mining CEO, David Boshoff, said work to remove the rock, known as the box-cut, was a significant milestone to have ticked off on the construction schedule.

“We are on track to export first coal in 2021,” Boshoff said.

“It’s great to see our big new gear, the Liebherr R 996B excavator and CAT 796 dump trucks, hard at work.

“In time they will reach the coal seam then we will be excavating coal as we need to remove around 4 m3 of rock for every tonne of coal we mine.

“As we move into this next phase of construction with more heavy machinery operating across the site, the safety of our people and contractors is my absolute priority.”

There are now more than 700 people working on the mine and rail project construction and numbers are growing as more contractors arrive to build the coal handling plant and to work on the railway.

“The expansion of our mine accommodation to 400 beds is complete to cater for the additional workforce and we will soon be able to accommodate another 1200 people in our temporary rail accommodation villages. We remain on track to deliver 1500 direct and 6750 indirect jobs.”

The Carmichael Mine will produce 10 million tpy of high-quality thermal coal, which will be used to generate affordable and reliable electricity for communities in India and South-East Asia.

The project’s low cost profile, such as its 4:1 strip ratio, the quality of the resource and forecast demand from our target markets of India and South-East Asia mean that the project’s economics are strong.

“We’re committed to using conventional truck and excavator mining techniques across the project,” Boshoff added.

“Our first five mining trucks and excavator have arrived on site and are operational and the assembly of our second excavator will commence in the coming weeks.

“We will also add more than a dozen mining trucks to our fleet over the coming months. The trucks will be assembled in Mackay, with each taking a team of about 40 men and women up to 10 weeks to put together before they are transported more than 300 km to site.”

Read the article online at: https://www.worldcoal.com/power/16072020/adani-starts-work-on-carmichael-mine/

You might also like

EMI

Electrification in Mining virtual conference

Join us on 16 April 2024 for Global Mining Review's first Electrification in Mining event is an interactive virtual conference, focusing on electrification as the future of sustainable mining and exploring the innovative approaches and technologies being developed to facilitate its implementation.

Register for FREE »

 
 
 

Embed article link: (copy the HTML code below):