Erdenet Rail Terminal FEED study completed

Published by , Editor
World Coal,


Aspire Mining Ltd is focused on developing metallurgical coal assets in Mongolia, primarily its wholly owned Ovoot Coking Coal Project (OCCP).

The company has advised that O2 Mining Ltd (O2) has completed Stage 2 of the FEED study for the Erdenet Rail Terminal (ERT) infrastructure and issued its report outlining the design and cost estimate (FEED study).

Key outcomes from Stage 2 of the FEED study include:

  • Conceptual designs for process infrastructure including train loadout facility of 1700 tph, enclosed storage of 58 500 t, and truck unload facility of 750 tph nominal capacities.
  • Conceptual designs for all non-process related supporting commercial and residential facilities, including the internal road network, site lighting and security, raw and wastewater reticulation, and electricity supply.
  • Preparation of all conceptual designs compliant with the Construction Code of Mongolia and the National Fire Protection Authority (NFPA) requirements in relation to the process infrastructure.
  • Optimisation of infrastructure layout allowing for future expansion, potentially enabling the doubling of the throughput with minimal additional capital expenditure and indicatively a one-third reduction in unit operating cost.
  • Engineering supportive of -10 – +25% accuracy of capital and operating cost estimates. The wide range reflects the current difficulties in securing firm quotations.
  • Forecast total construction schedule of 15 months, including eight months pre-construction procurement, permitting and detailed design and seven months on-ground construction activity involving up to 170 construction workers.
  • Total capital cost estimated for construction of the ERT infrastructure is US$17.7 million, including an EPC contract allowance of US$2.3 million and excluding owner’s costs such as for further studies, permitting and tendering.

FEED study overview

O2 has completed Stage 2 of the FEED study on the ERT infrastructure. The final report has been issued outlining its proposed design, and the estimated capital cost, construction schedule and operating costs.

Stage 1 of the FEED study was completed in July 2021. It comprised a trade-off study evaluating various potential concepts and technologies for transloading of washed metallurgical coal from road trucks to rail wagons. Each concept included application of technologies focused on containing potential dust generation and incorporated measures providing system redundancies to ensure that trucking activities would not be interrupted.

Stage 2 has built upon the learnings and outcomes from Stage 1 in respect to refining, designing, and estimating the most appropriate concepts and technologies identified. The resultant ERT designed infrastructure includes:

  • Enclosed truck unload facility capable of accepting side tipping coal trucks and receiving washed product coal at 750 tph nominal capacity for transfer via a covered conveyor to stockpile.
  • Enclosed coal storage building for 58 500 t nominal capacity.
  • Underground coal reclaim system and covered conveyors to train loadout facility with nominal capacity at 1200 tph.
  • Train loadout facility including surge bin with nominal capacity of 1700 tph (based upon expected maximum train payload).
  • Residential (accommodation), commercial (warehouse, office, workshop, security) and utilities (water, wastewater, heating, and electricity) supporting infrastructure.

The ERT infrastructure is intended to be situated on a site adjacent to the Erdenet to Salkhit railway line, which connects with the Trans Mongolian Railway in Salkhit. The FEED study does not include the design or cost estimation of the trackwork infrastructure required to connect onto this line.

Capital and operating cost estimates were prepared in alignment with Class III estimate guidelines from the Association for the Advancement of Cost Engineering (AACE) and are considered accurate to -10 – +25% as at the end of March 2022. The total capital cost estimated to construct the facility is US$17.7 million. This assumes that construction activities are conducted under an EPC contract. The total capital cost includes US$2.3 million in EPC contract margin and overhead.

On the ground construction and commissioning works are scheduled to be completed within seven months following approximately eight months of pre-construction activities including detailed design, obtaining construction permits and regulatory approvals and equipment procurement, for a total of 15 months from EPC contractor engagement. Proximity to the city of Erdenet will benefit construction activities on the basis that this industrial city hosts a range of skilled labour, materials supply and subcontract services. A maximum construction workforce of approximately 170 workers will be required.

On basis that the ERT will operate 24 hours per day 365 days per year, a total operational workforce of approximately 80 full time equivalent personnel will be required, split across four panels working 12 hour shifts in accordance with requirements of the Labour Law of Mongolia (2021). At throughput capacity in support of the maximum initial expected CHPP output, a total unit operating cost of US$1.07/t handled from road truck to rail wagon is estimated, of which the majority comprises electricity (sourced from the grid at published rates) and labour including oncosts.

Pre-construction activities, including preparation of a government compliant feasibility study, and community engagement as part of the environmental impact assessment process, can now commence. Support from local government is anticipated on the basis that construction will result in the creation of significant employment and commercial opportunities for local residents.

The company is continuing to liaise with the Ministry of Nature, Environment and Tourism in relation to the approval of the company’s detailed environmental impact assessment for the Ovoot Coal Mine, which underpins completion of the OCCP definitive feasibility study.

Read the article online at: https://www.worldcoal.com/coal/21062022/erdenet-rail-terminal-feed-study-completed/

You might also like

EMI

Electrification in Mining virtual conference

Join us on 16 April 2024 for Global Mining Review's first Electrification in Mining event is an interactive virtual conference, focusing on electrification as the future of sustainable mining and exploring the innovative approaches and technologies being developed to facilitate its implementation.

Register for FREE »

 
 
 

Embed article link: (copy the HTML code below):