Skip to main content

Put to the test

Published by
World Coal,


Dorstfontein coal mine in Witbank, South Africa, is located approximately 2 hrs from Johannesburg. In October 2011, a two-man engineering team from PEBCO, US, travelled to South Africa to spend approximately one month performing start-up testing on Dorstfontein’s PEBCO batch weigh train loading system. Before start-up, the loading system needed to be completely installed, all field piping installed and flushed, all electrical wiring pulled, landed, verified and rung out, and continuity checks performed.

Put to the test

The first couple of days of testing entailed a complete system walk down of mechanical, hydraulic and electrical areas. Next, internal cleanliness of the HPU reservoir needed to be verified, then filling of the hydraulic reservoir. Pressure testing came next for all hydraulic fittings, piping and hosing by increasing system pressure at intervals until full system pressure had been reached.

Operational testing of the various gates and the telescoping chute by manual actuation of the control valves was tested. This was carried out in several steps and worked up to full system pressure.

Once the team was 100% satisfied with the manual operation of the system, team members checked the controls to verify that the same gate or chute functions exist via the control system. Once verified, the team moved on to fine tune gate movements by adjusting the ECM4-L2 amplifier cards for the electro-hydraulic control system.

Because the accumulators had not been charged and/or offline up to this point, they were then charged with nitrogen to bring them online. The full system pressure operational testing was then repeated.

After completion of the above and when all of the field welding has been completed and lightening protection installed, the team was able to move on to removing the dummy load cells and replacing them with the actual load cells. In order to properly adjust and shim the load cells, test weights needed to be hung off of the weigh flask and tested for accurate calibration of the weighing system. A surge bin was filled with coal and a railcar was placed under the loading system for hauling off the material used in the calibration process.

Once the weigh flask was certified, the team was ready to run test trains in order to verify photo-eye placement. At that point, the conveyor feed system and conveyor was in full operational status.

 

Overview of operation

  • Arriving trains are 100 cars in length with each car length 40 ft long. Car sizes are not mixed.
  • Loading time could not exceed 2.5 hrs.
  • The railcar types are CCL-7 and CCL-8 with an 84 000 kg maximum load, an average 20 250 kg tare and a 104 000 kg gross weight. Although it had been stated that the CCL-3 (small railcars) would not be pulled through the loadout, the system has the capability to load the CCL-3 with a 58 000 kg maximum load, an average 21 200 kg tare and an 80 000 kg gross weight.
  • Permitted overload on each car is 500 kg and underload is 250 kg.
  • Individual car weight requirements are a minimum of 95% of the entire train, based on constant train speed through the loadout station and constant material flow characteristics.
  • The load has to be centralised as the railcar was being filled, otherwise spillage and underloading would occur.
  • Cars entering the loading area are rolled across two pairs of transducers. Individual axle weights are read and logged into the computer system. The control system compensates for any residual material already in the railcar.
  • An operator checks that all functions are normal on the hydraulic power unit, that the control system is receiving tare scale information and that the reclaim system is up and running.
  • The telescoping chute is then moved horizontally from its park position to its load position. Vertical chute positioning is automatic, based on chute position feedback from the integral LDT in the telescoping chute lift cylinder. The operator always has the capability to make manual adjustments to the chute height by simply moving the ‘chute-up’ joystick. However, once the joystick is moved, the system is no longer in automatic mode.
  • When the ‘batch-ready’ light comes on, the operator instructs the train operator to proceed at the set loading speed.
  • When the first railcar blocks the ‘open gate’ photo-eye, the weight flask discharge gate opens and the coal is flood loaded into the railcar.
  • Once the gate is shut and the weigh flask stable, the next batch for railcar #2 is pulled and the process is repeated until the entire train is loaded.

The batch weigh train loading system has two modes of operation:

  1. Fully-automatic mode, which requires no input from an operator after the initial spotting of the first car.
  2. Manual mode, which bypasses all photo eyes, including ‘end-of-car’, and requires a human operator to manually adjust the chute and gate positions.

 

PLC control

 

In order to maintain the highest level of integrity and speed of response, a programmable logic controller (PLC) provides control and interfacing with the real-world devices, such as gates, photo eyes and other critical components of the system. Where necessary, this system, in conjunction with the programme, adheres to a fail-safe principal, such that, in the event of power loss during loading, there can be no spillage and the system will automatically reset on power up. Interaction between the PLC and the scale will be via direct serial cable connection, ensuring the fastest possible response as required to obtain optimum accuracy.

In recent correspondence with Patrick Smith, Scoping & Business Improvement, FLSmidth (Pty) Ltd South Africa, Smith indicated, “the PLC systems you provided for Dorstfontein is working like a charm”.

 

Note

 

Written by Ralph Story, PEBCO Inc., USA. This article first appeared in World Coal December. To read this and much more, register to receive a copy here.

Read the article online at: https://www.worldcoal.com/special-reports/08122016/put-to-the-test/


 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

South Africa coal news