Former Derbyshire drift mine made safe to protect public and environment

Published by , Editorial Assistant
World Coal,


After Eckington Colliery in Derbyshire unexpectedly closed in January 2019, the Coal Authority carried out a detailed programme of works to keep people safe and protect the environment.

The drift mine had been worked by two roadways that ran about 30 m beneath a railway line linking London and Sheffield.

To ensure this major route was not damaged by future subsidence linked to the former mining operation, roadways needed to be sealed and packed to permanently stabilise the ground.

Detailed investigations were carried out to assess the rate at which the water within the mine would recharge once the site was no longer active. This showed that swift action was required to complete the work before rapidly rising water levels from underground springs made any solution more difficult and costly.

Poor access to the site – via a weight-restricted bridge over the River Rother – added further complications to the project.

Senior Engineer Zoe Rose-Higgins worked on the project with colleagues from across the Coal Authority and other relevant bodies, including Network Rail and North East Derbyshire District Council.

She said: “There are underground springs at this site, so when the mine was open they had a series of pumps which were constantly running to control the water levels. “Once the mine closed the pumps were inoperable, so rising water levels meant we needed to get works agreed quickly and put an engineering solution in place.

“We designed stops, which are reinforced concrete blockwork retaining walls, about 140 m inside each roadway. The drifts followed the coal seam and, because of the steep angle, we could essentially use gravity to fill them with foamed concrete.”

Concrete was used as, due to the pillar and stall working methods employed at the mine, there was no suitable waste material on the surface.

An 80 m section in each roadway was packed, using a total of 1000 m2 of concrete, which was poured and allowed to set in sections so the walls wouldn’t collapse.

The lack of mechanical haulage systems on the site meant much of the work was done by hand and our contractor employed former miners on the project to undertake this vital work.

Zoe said: “One of the technical challenges was pumping the concrete to where we needed it. We couldn’t take trucks over the bridge, so we had to park in a yard on the other side of the railway tracks – around 300 m away – and use a specialist pump to undertake the work.”

Finally the entrances were dug out and re-profiled to close the roadways off and provide a permanent solution to keep people safe and protect the local environment.

Read the article online at: https://www.worldcoal.com/power/23012020/former-derbyshire-drift-mine-made-safe-to-protect-public-and-environment/

You might also like

EMI

Electrification in Mining virtual conference

Join us on 16 April 2024 for Global Mining Review's first Electrification in Mining event is an interactive virtual conference, focusing on electrification as the future of sustainable mining and exploring the innovative approaches and technologies being developed to facilitate its implementation.

Register for FREE »

 
 
 

Embed article link: (copy the HTML code below):