TAKRAF delivers cross conveyor system on time

Published by , Editor
World Coal,


TAKRAF GmbH

In August 2014, TAKRAF GmbH received an order from Vattenfall Europe Mining AG for the supply and installation of the new cross-conveyor system for the F60 conveyor bridge at the opencast coal mine at Welzow-Süd/Brandenburg. The scope of services included the fabrication respectively conversion of hopper cars and chassis, as well as the scrapping of system components that would no longer be used. The special challenge of the project was the tight schedule. Thanks to the commitment and the long-standing experience of all experts involved at Vattenfall and TAKRAF, the system could be delivered after ten months, as planned.

Production started immediately after the award of the contract and the first parts arrived at the site after five months. Close coordination between the fabrication and erection teams meant that all operational obstacles were managed in order to meet the demanding schedule. The hopper cars were relocated from April 2015 onwards. Thus an important milestone with regard to the mine operation was reached on time.

By end of June 2015, the cross-conveyor system had been further assembled. The scrapping, conversion and adaptation work, which was carried out in parallel, was executed with the help of a TAKRAF transport crawler with a load capacity of 250 t, which had been supplied by TAKRAF to Vattenfall earlier. The next milestone was in May 2015, again on schedule, when the complete conveyor bridge was moved by about 10 m in order to couple the new cross-conveyor system to the bridge. The scope of work also included the renovation of the lubrication system, as well as corrosion protection at the construction site.


Figure: Pre-assembly of the cross-conveyor system

All personnel involved in the project team in the fields of engineering, fabrication and site erection worked closely together, enabling the successful realisation of the contract within the pre-determined schedule, benefitting from the expertise developed over many years in complex reconstruction and modernisation works, as e.g. changing the tension tie rods on the conveyor bridge in the Jänschwalde opencast mine. The cross-conveyor system was completed in June 2015.

After three days of commissioning by experts from Vattenfall, the conveyor bridge went back into mine service. TAKRAF is already working on another project at Vattenfall, i.e. changing the large bogie and the roller table at the F60 conveyor bridge at open cast mine Nochten.

Edited by .

Read the article online at: https://www.worldcoal.com/handling/24092015/takraf-delivers-cross-conveyor-system-on-time-2910/

You might also like

EMI

Electrification in Mining virtual conference

Join us on 16 April 2024 for Global Mining Review's first Electrification in Mining event is an interactive virtual conference, focusing on electrification as the future of sustainable mining and exploring the innovative approaches and technologies being developed to facilitate its implementation.

Register for FREE »

 
 
 

Embed article link: (copy the HTML code below):